Full Crew
10/04/2017 AD built
Soi begins electrical and plumbing systems, allowing the masons to continue finishing the internal walls.
Also, door jambs and even the external bathroom wall are begun. An incredible flurry of work today.
Subjects Who or What built?
Objects To Whom or What was built?
-
Our House (Sisaket Bungalow) Our house in Sisaket is ...
Timelines (that include this event)
Attachments
Soi Begins Electrical The walls need to be routed out for each electrical box as well as the conduit between them.
Electric Around Pillars At every pillar, the conduit must run vertically to the ceiling
Ja Starts Bathroom Now that Soi has given the OK, the bathroom exterior wall can be started by Ja
Door & Ceiling Materials Plywood and metal structure for the sub-ceiling arrives along with interior bedroom doors and jambs
Kitchen Drain With Soi here, the plumbing also begins - here is the kitchen drain exiting the back wall of the house
Bedroom Door Jamb Por Am & Ja install the bedroom door jambs.
Hive of Activity With five workers the site is buzzing
Poor Light Wiring Soi cuts the walls for exterior lighting
Front Bedroom Door Withe the door jambs in the bedrooms they are now really rooms
Events in 2017 MORE
![Shane Bow](/uploads/ads/5.jpg)
![Thai Hangman](/uploads/ads/9.jpg)
![Thai Drills](/uploads/ads/10.jpg)
![alasnome](/uploads/ads/12.jpg)
![sirijanda](/uploads/ads/13.jpg)
![sirijanda](/uploads/ads/14.jpg)
![CrossFit F3](/uploads/ads/15.jpg)
![dcce](/uploads/ads/19.jpg)